Authorization/Permit: Power Generation Permit
General Description
  • In order for a company to be able to generate power by renewable or non-renewable sources.
Responsible Authority Resolution Term
  • Energy Regulatory Commission (“CRE”)
  • Approximately 3 months.
Requirements
  1. Power generation application according to the official format issued by the CRE;
  2. Incorporation deed and powers of attorney of the legal representative;
  3. General project description;
  4. Documents of proof of technical capability;
  5. Acknowledgment by the Ministry of Energy of the filing of the Social Impact Evaluation;
  6. Estimated Work Program and Dates;
  7. Business Plan;
  8. Copy of the governmental fees receipt;
  9. Documents of proof of Financial Capability.
Permit Term
  • 30 years.
Additional Information
  • This permit can only be granted by the CRE.
  • The application shall be filed before the Electronic