It is well known that claims brought for a breach of the 2006 Public Contracts Regulations must be made within a tight 3 month time limit. There have been two recent cases Brent London Borough Council v Risk Management Partners Ltd, [2009] EWCA Civ 490 and Amaryllis v HM Treasury, [2009] EWHC 962 (TCC) which have considered this principle.

Regulation 47(7) makes it clear that there is a two step process:

(7) Proceedings under this regulation must not be brought unless –

  1. the economic operator bringing the proceedings has informed the contracting authority ... of the breach or apprehended breach of the duty owed to it.....and of its intention to bring proceedings under this regulation in respect of it; and
  2. those proceedings are brought promptly and in any event within 3 months from the date when the grounds for the bringing of the proceedings first arose unless the court considers that there is good reason for extending the period within which the proceedings may be brought.

Brent London Borough Council v Risk Management Partners Ltd

The Brent case came before the Court of Appeal. Here RMP claimed that certain contracts of insurance had been awarded by Brent Authority to the London Mutual Ltd ("LAML") outside of a tender process in which they participated. It is important to note that RMP were only making a claim for damages. Amongst other issues, Brent said that the claims were started more than three months after the date on which the grounds for bringing the proceedings first arose. In particular, Brent submitted that grounds for bringing proceedings existed (and that time therefore started to run) in November 2006 when RMP were told that Brent was obtaining insurance elsewhere. Proceedings were not commenced until 6 June 2007. If Brent was right, RMP were well out of time.

Pill LJ noted that:

When considering when grounds for proceedings first arose it is necessary to bear in mind that the Regulations prescribe the procedure which a contracting authority must follow before entering into a contract with a supplier of goods or services... It follows that a failure by the contracting authority to comply with any step in the required procedure involves a breach of duty sufficient to support a claim under the Regulations. Moreover, because the procedure governs the whole process from the formation of the intention to procure goods or services to the award of the contract and is structured in a way that is intended to ensure equal treatment and transparency throughout, a failure to comply with the procedure at any stage inevitably undermines the integrity of all that follows.

In doing so, he expressly recognized the problem that whilst grounds for bringing proceedings may exist well before the procedure reaches the award of a contract, the Regulations do not expressly identify the point at which that will occur. The relevant chronology was as follows:

  1. On 9 October 2006, Brent resolved in principle to participate in LAML;
  2. On 7 November 2006, the RMP were told by Brent's brokers that Brent "had committed to going into the Mutual" but that there was uncertainty whether it would be ready by the next renewal date (1 April 2007) and there would be some insurance that would be sought outside it anyway. Accordingly there was to be a full tender exercise;
  3. At a meeting on 13 November 2006, Brent resolved to approve participation in LAML;
  4. In December 2006 Brent invited tenders for cover generally from 1 April 2007;
  5. On 18 January 2007, Brent began membership with LAML;
  6. Because incorrect documentation had been used, a replacement invitation to tender was issued on 1 February 2007. RMP tendered in time; LAML did not participate;
  7. On 7 March 2007 a representative of Brent told RMP, informally, that Brent's insurance would be dealt with through LAML. In response RMP looked at Brent's website and located the decision of 13 November 2006;
  8. RMP sought formal confirmation by letter of 19 March 2007, and received it by letter from Brent of 27 March;
  9. Brent made payments to LAML from 16 March onwards;
  10. By letter of 4 May 2007 RMP's solicitors raised with Brent the question of breach of the regulations;
  11. Proceedings were begun on 6 June 2007.

Brent submitted that grounds for the bringing of proceedings first arose in November 2006 when they resolved to approve participation in LAML or, alternatively, on 18 January 2007 when they became a member of LAML. Brent said that either time runs or it does not and a claimant cannot (if out of time from the date a breach has been apprehended) improve his position by waiting for the actual breach to occur.

The Judge at first instance Stanley Burnton LJ held that:

"In my judgment, therefore, for the purposes of the Regulations in the present case "grounds for the bringing of the proceedings" first arose when the breach which forms the subject of the claim occurred. It would have been different if the claim were for an injunction to restrain a breach of the Regulations; but it is not.

It is therefore necessary to determine when the breach of the Regulations first occurred. It seems to me it was when the appellant abandoned the tender process and awarded the contracts to LAML. That occurred in March 2007. Until then, it could have lawfully awarded the insurance contracts to a company participating in the tender processs."

The Court of Appeal agreed. The key here was the date when Brent abandoned the tendering process and made payments to LAML. Only then were Brent committed to taking policies from LAML. Before March 2007, RMP had not sustained the damage which was the basis of their claim. It may be that RMP could earlier have made an application for interim relief but that did not start time running on the claim actually made.

In any event, in the view of the Court of Appeal, there was good reason for extending the period within which the proceedings could have been brought, within the meaning of regulation 47(7)(b). As late as February 2007, Brent issued an invitation to tender and, late in the month, RMP submitted a tender in response within time. Accordingly, Brent should not be allowed to defeat, on the ground of delay, the claim brought by RMP at the time it was.

Amaryllis v HM Treasury

Here Amaryllis submitted a pre-qualification questionnaire in respect of a framework agreement for the supply and installation of furniture on a national basis. The agreement was to be divided into six lots. Amaryllis was informed by letter on 17 March 2008, that it had come though the first stage on four of the lots. On 9 April 2008 there was a meeting between the parties at which the question of Amaryllis' unsuccessful tender on Lot 1 was raised. Although there was a considerable dispute as to the way in which the topic was raised, it appeared to Mr Justice Coulson to be "beyond argument" that Amaryllis wanted to know why their bid on Lot 1 was unsuccessful and that HMT did not give them very much information in response. Amaryllis wrote to HMT on 15 April 2008 seeking an explanation. HMT responded on 21 April 2008 in a letter which the Judge again felt did not provide a clear or cogent explanation as to how and why Amaryllis had been unsuccessful.

On 23 May 2008, Amaryllis said it would not be submitting a tender for Lots 2-5 because it had no confidence that any tender submissions would be given a fair and valid assessment. On 4 June 2008, Amaryllis indicated its intentions to bring proceedings, but again requested reasons as to why the Lot 1 bid was rejected. Amaryllis were of the view that they had to commence proceedings by 16 June 2008, 3 months after they received notice of their rejection on Lot 1. They duly did so even though HMT had not provided any response to the June letter. Amaryllis made a number of claims. First, it appeared that no marks were allocated to section F which dealt with previous experience when the tender information stated that all sections would be marked. Amaryllis also complained that HMT had evaluated the responses without having informed any tenderer as to the relative importance ascribed to each question - in particular the importance and weighting to be given to the environmental management issues. The Judge described this as being a bit like being required to do an exam without knowing what marks were available to any given question. Finally, Amaryllis complained that it was given a zero under a business heading on the basis that it brought in furniture rather than manufacture it itself.

HMT said that Amaryllis were not entitled to bring a claim because it had not provided notice of its intentions and had not brought its claim in time. As stated above, under Regulation 47(7)(a) of the Public Contracts Regulations 2006, a party is required to provide written notice of the breach and its intentions to bring proceedings. Here, Mr Justice Coulson thought that adequate notice was provided. The regulations were clearly identified in the June 2008 letter and both Amaryllis' intentions and the actual breach complained of were clearly identified. Finally, the Judge said that the adequacy of the notice had to be considered against the backdrop of the (lack of) information provided by HMT.

Further, HMT said that Amaryllis did not act promptly. The Judge said that the starting point is when the specific breach of the regulations actually occurred. That will often be when the actual decision is made to exclude a tenderer. However, here the grounds for bringing the proceedings first arose when the irrevocable decision was taken by HMT to exclude Amaryllis on Lot 1. Therefore, the relevant date was the date on which HMT wrote to inform Amaryllis that its bid had been unsuccessful, 17 March 2008. Note too that the three month period is intended to be a maximum period. Even if the proceedings have been commenced within that period, it is still necessary for the court to consider whether or not they have been commenced "promptly". Therefore, here, even though proceedings were brought within the three month period, the Judge had to review what had actually happened.

Between 17 March and 22 April 2008, there was no culpable delay on the part of Amaryllis. It received a letter at the start of Easter week and a meeting was arranged in the first full working week after Easter. Amaryllis then wrote on 15 April 2008, receiving an inadequate answer on 22 April 2008. HMT focussed on the fact that between 22 April 2008 and 4 June 2008, little, if anything, outwardly happened to progress this matter. However, the Judge disagreed that nothing relevant happened during this period. The evidence was clear that Amaryllis was involved in making enquiries with other potential tenderers to try and piece together the possible reasons for their exclusion. Amaryllis knew that it had been excluded. It was entitled to gather what information it could about the reasons for its exclusion and then balance the results of those researches against the risk of commencing proceedings against a party with whom it had an ongoing commercial relationship. Finally no criticism of Amaryllis could be made of the period 4 June and 16 June 2008, the period where it was awaiting a response to a letter from HMT.

In addition, the Judge thought it fair to compare Amaryllis' speed of reaction with HMT's conduct during the relevant period. HMT was anything but prompt. Indeed, had it been necessary to consider whether Amaryllis needed any extension of time, Mr Justice Coulson felt that HMT's conduct during the relevant period was likely to have been the main cause of any delay and that no prejudice would have been suffered by HMT as a consequence of that delay. Therefore Amaryllis would have had a real prospect of demonstrating good reason for any delay, had it been necessary. Accordingly, the Judge concluded that Amaryllis was duly entitled to pursue its claim against HMT.

Conclusion

Both these cases demonstrate the importance if you intend to make a challenge to a publically procured project, of acting promptly. Whilst it is true that both these cases also suggest that the courts will take a fair and reasonable approach in deciding whether the 3 month time limit has been complied with or not, you must bear in mind that they will only do so, if it is appropriate in all the circumstances.

To read further articles by Jeremy Glover, please visit www.fenwickelliott.co.uk.

To see further articles on matters relating to construction, engineering and energy projects, please visit www.fenwickelliott.co.uk.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.